CONCRETE DOOR FRAMES
|
System Components
|
Initial Cost Structure
|
|
|
Critical Factors
1. Curing
2. Quality of sand for concrete
3. Provision of holes at the right place for
fixing door shutters
4. Holes for fixing the door shutter
|
Tools Used
1. Trowel
2. Wooden float
3. Straight float
|
DO’S
|
DON’T’S
|
1. Frames should be cured for 14 days
2. Mortar should be used within 30
minutes of adding water to mix
3. Frames should be stacked properly
|
1. Cavities should not be left in the frame
during casting
2. Fine sand should not be used
3. Excess water should not be added to
the concrete
|
Construction Process
|
Take measured quantities of cement, sand and aggregates and mix the concrete
|
Clean and assemble the mould
|
Place reinforcement in the mould and fill concrete
|
Insert a PVC pipe at the center of the post to fix door latch
|
|
|
|
|
Compact the concrete with trowel to get uniform thickness to the frame
|
Remove the mould
|
Finish the edges with straight edge
|
Finish the edges with wooden float
|
|
|
|
|
Clean the concrete from the PVC pipe provided for the door latch
|
Make hole on the post to fix door hinges
|
Cure the frames for 14 days
|
Stack the frames
|
|
|
|
|
Erect RCC door frames in the house
|
A house with a RCC door frame
|
A house with RCC door frame with wooden shutters
|
|
|
|
|
|
|
|