RCC PILE FOUNDATION
|
System Components
|
Initial Cost Structure
|
|
|
Critical Factors
1. Depth of pile and number of reamers
2. Quality of soil
3. Water table level
4. Clear cover of concrete to reinforcement
|
Tools Used
1. Crow Bar 4. Reamer
2. Spade 5. Tape
3. Basket
|
DO’S
|
DON’T’S
|
1. Pile should be cast immediately after boring to avoid collapse of bore wall
2. Depth of pile should be checked properly
3. Concrete should be properly compacted
|
1. Fine sand should not be used for concreting
2. Concrete should not be used for a designload
more than 80 tones
|
Construction Process
|
Set out the location for bores
|
Mark the area for pile foundations
|
Dig the bore to 30cm deep using crow bar
|
Wet the bore and dig with reamer
|
Apply force over the reamer for digging bore
|
Remove the mud from reamer at regular intervals
|
Dig the bore to the required depth
|
Check the depth of the bore
|
Tie the reinforcement
|
Place the reinforcement in the bore
|
Fill the bore with cement concrete
|
|
|
|